On November 26, 2021 EPCG AD Nikšić launched a simple procurement procedure for development of the Preliminary Design for Pljevlja distant heating Project 'For worm and clean Pljevlja – construction of a primary heating pipeline from TPP Pljevlja up to the town.
Bid opening is scheduled for December 2, 2021.
Mr. Nikola Rovčanin, the EPCG CEO, states that after selection of the best bidder, a Designer prepares the project within 45 days deadline i.e. by the end of January 2022, after which date the project undergoes review and obtaining the UT conditions.
Completion of these activities is expected by the end of February 2022, and then we will launch a public invitation to tender for development of Detailed Design and construction of a primary heating pipeline from TPP Pljevlja up to the town, on a Design Build principle, highlights Rovčanin.
The expected Time schedule envisages that after selection of the best bidder, a 60-day period for Detailed Design preparation and 20-day period for review thereof comes execution of works.
As confirmed by the Chief Executive Officer, EPCG has planned and earmarked in its Budget the amount of 2.5 M€ for the Project of distant heating of Pljevlja -'For warm and clean Pljevlja'.
Press Releases
Announcements from other categories
-
EPCG BECOMES GENERAL SPONSOR OF MONTENEGRO’S VOLLEYBALL FEDERATION
2 years 9 months -
EPCG DONATED AUDIOMETER TO THE PRIMARY HEALTH CARE CENTRE OF BUDVA MUNICIPALITY
3 years 1 month -
30 million euros for dividend payment
3 years 5 months
-
11.12.23
Public Invitation for EPCG-Željezara Nikšić
-
26.07.23
DJUKANOVIC: PERSPECTIVES ON ELECTRICITY GENERATED BY SOLAR POWER PLANTS AS PART OF SOLARI 3000+ AND 500+ PROJECT
-
28.10.22
XXV EXTRAORDINARY EPCG SHAREHOLDERS’ MEETING TOOK PLACE
-
28.10.22
FROM THE PROFESSIONAL POINT OF VIEW: EPCG IN THE CONTEXT OF THE GLOBAL ENERGY CRISIS
- Home
- Media center
- Press Releases
- EPCG LAUNCHED A PUBLIC INVITATION TO TENDER FOR DEVELOPMENT OF PRELIMINARY DESIGN OF DISTANT HEATING OF PLJEVLJA